Class exercise CFCP-2025-001

Metro Plaza Foundation Construction

Four foundation pads, twelve resources and £371,621 of cost to load. Build the programme, give every activity its crew, plant and materials, then update it twice and read what the earned value is telling you.

Programme
24 days
Budget
£371,621
Activities
22
Updates
2

Register to open the exercise

Cohort 4 students. Your tutor shares the class password in the cohort group.

UK mobile, or any number with its country code.

Details are never shared. To have them removed, ask your tutor in the cohort group.

Fourteen seconds of the whole exercise

The programme draws itself, the budget loads to £371,621 and the baseline S-curve climbs. By the end of the class you will have built every frame of it in P6.

Five trades, four pads, one concrete crew

Each pad runs the same sequence. The pours are chained, so one crew moves from North to South to East to West, and the critical path hops across the site with it.

Site preparation, then excavation

Clear, grade, dig

Site crew, then an excavator with its operator and three labourers. Excavation sets the pace for everything behind it.

Formwork

Shutters and props

Carpenters and formwork ply. Two gangs on site, four pads that want them at once. You will find the clash in the resource profile.

Reinforcement

Fix the steel

Steel is a material resource priced per tonne. One pad fixes it with a smaller gang: same activity, different resource need.

Concrete

Pour and cure

Ready-mix by the cubic yard, a crew of four and a truck. Four pours in sequence close the job on 01/08/2025.